In the Matter of the Application of Buckeye Wind LLC, Case No. 2015-1715
Ohio Power Siting Board
ISSUES:
- To extend beyond the five-year deadline to begin construction that is included in an Ohio Power Siting Board certificate authorizing a wind turbine electric generation facility, must the owner submit an application to amend the certificate, which triggers a board staff investigation?
- Does R.C. Chapter 4609 give the Ohio Power Siting Board authority to approve an extension to a construction certificate by motion if the board finds there is no proposed change in the construction plans for the facility?